Live-verified, not a concept mockup
Three proof points, run against a live P6 instance
Every result below was produced by Stoichos operating directly against a real Primavera P6 EPPM database — not a simulated environment or a scripted demo.
Foundational proof
A single duration change, cascaded correctly
On a live P6 EPPM instance, Stoichos looked up a real project, changed an activity's duration from 160 to 240 hours, and ran a full F9 recalculation. The three downstream activities each shifted forward by exactly 14 calendar days — the correct cascade for a 10-working-day increase on a 5-day work week — with every activity retaining its correct duration afterward.
No spreadsheet export. No manual re-entry. No P6 Professional client UI.
160→240hours changed
+14days × 3 activities
1F9 recalculation
Full-scale proof
A complete project, built live from scratch
Stoichos built a complete project live — roughly 30 activities across 8 WBS nodes, ~34 relationships, up to 16 labor, non-labor, and material resources, ~29 resource assignments with computed costs, and multiple activity code categories — with schedule dates and costs matching a hand-verified training manual's own answer key. It then enabled multiple float paths, ran F9, and produced a correct float-path report — six distinct paths, Gantt-format, with Total Float — directly from the live schedule.
~30activities / 8 WBS nodes
~29resource assignments
6float paths reported
End-to-end training exercise
The same curriculum a junior scheduler learns on
Given a supplied dummy schedule, Stoichos worked a complete Primavera P6 training exercise end to end — adding activities, building the relationship network, assigning resources, running F9, and completing every intermediate step the exercise calls for. This is the same path a junior scheduler already grounded in critical path method follows when learning the software itself: the standard route from understanding CPM to operating P6. Every step was performed against the live database through the operations a scheduler performs in the P6 client, not by editing an exported file.
Exercise sequence
Activities
→
Relationships
→
Resources
→
F9
→
Verified result